Talk to us
The platform

Eight stages. One record.

Every stage below earns its place on its own. Underneath, they all write to the same building. Here is the whole thread, end to end.

00
Land & Feasibility
ENVELOPE PLOT
ASK KORBEL
What was our ward number?
Ward 42 — from the title deed.
Setback required in that area?
4.5 m front · 3 m rear & sides.
ASK KORBEL
What's the maximum sq ft we can get out of this land?
FAR 2.5 on 19,440 sq ft after setbacks — ≈ 48,600 sq ft, height cap 24 m.
LAND VAULT · PERMISSION CHECK
Title deed
Encumbrance certificate
Zoning clearance
Access documentsOPEN ↵

Know the envelope before you own the risk.

The plot is bought on a broker's word. What it will actually let you build arrives months later, from a consultant, in a PDF.

Upload the land sketch and Korbel walks you through the questions that matter: setbacks, zoning, height limits, the permissible envelope. Where government portals allow it, the regulatory data is pulled in directly instead of keyed by hand. The land papers go into a locked vault with its own door, not a lawyer's drawer.

You know what the plot permits before the architect draws a line.

01
Design
ARCH STR MEP FEDERATED MODEL
LOD GAPS · WHATSAPP · DESIGN TEAM
Beam STR-B-1204 has no rebar detail — LOD 350 needs it.
Door D-114, floor 3 — fire rating missing.
Uploading the revised sheet now.
2 of 14 gaps remaining
CLASH DETECTION · CONTINUOUS
34 clashes detected
2 critical — routed to BIM manager
9 major — ranked for review
23 auto-resolved

One building, not a thousand pages.

The architect works in one tool, the structural engineer in another, MEP in a third. Each drawing is right on its own. Together, they disagree, and the disagreement is found on site.

Korbel takes the drawings as they come, from AutoCAD, Revit, ArchiCAD, MicroStation and the rest, and builds them into one federated model. Where the model has gaps, it chases the design team on WhatsApp until they close. Clash detection never sleeps: the obvious conflicts resolve themselves, the hard ones rank for review, and a Korbel BIM manager handles what the system cannot. When the machine and the drawing disagree, a person decides.

There is one version of the building, and everyone is looking at it. Including you. You interact with the design directly, not with a print pile. Where a site warrants it, your field team walks the building in VR before it exists.

02
Plan & Cost
BOQ · FROM THE MODEL
Column C-204 · RCC M302.1 m³
Rebar Fe550 · Tower A186 t
Blockwork · L3–L99,420 m²
2,847 line items · element by element
SCHEDULE · FROM THE SEQUENCE
FoundationAUG–OCT
FrameOCT–MAR
MEPJAN–JUN
FinishesAPR–SEP
VENDOR RATES · LIVE · WEB + WHATSAPP
Steel Fe550₹62,400/t
Cement OPC 53₹412/bag
Shuttering crew₹680/m² ·
Rate book moves with the market
DESIGN CHANGE · CONSEQUENCES
Basement slab revised — +150 mm thickness.
Cost+₹18.4 L
Schedule+4 days
Landed in the team's thread — nobody went looking
NAME A DATE
Can we finish by 15 March?
Yes — with a second formwork crew from July.
The lift install stays 3 days, however many crews you throw at it.

The price and the programme come from the drawing. Not from memory.

The BoQ is generated from the model, element by element. The schedule is built from the physical order of the work, then crew sizes and shift patterns turn the sequence into dates. Vendor rates stay live: suppliers submit and refresh prices on the web and WhatsApp, and the project rate book moves with the market.

Then the part no spreadsheet does. Change one thing in the design, and the cost and schedule consequences land in the team's WhatsApp thread before anyone has to go looking. Name a completion date, and Korbel shows what capacity has to change to hit it, and refuses to lie to you. A lift install that takes three days takes three days, however many crews you throw at it.

Feed it your past projects once, plans, bills, invoices, and it prices the next one with your real regional costs, labour included.

03
Procure
BOQ BATCH B-07 · PO SCHEDULE
PO-118 · Rebar 24 tLEAD 6 WK
PO-119 · RMC 140 m³POUR 12 SEP
RELEASE ↵
Released — issued to vendors
AT THE GATE · CCTV + WAYBILL
CAM 1 · 18:02
CAM 2 · LOAD
Waybill WB-4471 · Rebar Fe55024.0 t
GENERATE GRN ↵
GRN-0871 created ✓
INVENTORY · FORECAST
Rebar Fe55014 days cover
Cement OPC 53 — 6 days cover
Needed for coming weeks480 bags · 21 OCT
RELEASE PO ↵

Buy what you drew. Catch it at the gate.

Purchase orders cut directly from the live BoQ, batched by lead time and pour window, sequenced just in time so your cash is on the job, not asleep in a stockyard.

The truck arrives. Challan scanned, load photographed, count taken, and the GRN writes itself against the exact elements the material belongs to. If what turned up is not what was ordered, you find out at the gate, not at month end. Invoices reconcile against GRNs, consumption tracks against the model, and site stock is checked against the next few weeks of schedule. Low stock, over-delivery, off-spec: each one lands in the team's thread as it happens.

04
Build
CCTV + LIDAR + DAILY REPORTS
CCTV · L9
LIDAR SCAN
Daily report — ▶ 0:42 voice · 6 photosL9 SLAB
Cross-checked · logged → 14 elements
YOUR PROJECTS
Marina Tower62%
Court Villas · Ph 238%
Axis Business Park81%
Progress as proven, not as reported
MARINA TOWER · PLAN VS ACTUAL
Critical pathL9 SLAB → FAÇADE → LIFT
PLAN68%
ACTUAL62%
−3 days on critical path · recoverable
SUBCONTRACTOR MILESTONES
Blockwork L1–L3 · Alpha Co.✓ 12 SEP
MEP first fix L2 · Volt Engg✓ 19 SEP
Waterproofing pods · SealtechDUE 30 SEP
Measured jointly · evidence attached
SMALL ADJUSTMENTS · LOGGED
Shift duct MEP-D-0412 — 4 in towards the lift.
Clash clear · CE + CM approved
+₹2,500 logged · model updated

Prove the work as it happens.

The site engineer sends a photo and a voice note from the slab. Korbel parses it, checks it, and marks the element complete. Every pour, every wall, every install, recorded against the thing itself, at the moment it happens.

Every morning, Korbel compares the building you planned with the building you have, and tells you where the two differ. The DPR writes itself from what was actually recorded, not from what someone remembers at 9pm. And when it is time to bill, the running bill drafts itself against completed elements, evidence attached. Built to be signed, not disputed.

05
Handover
SNAG REGISTER
Door D-114 · photo + voice note→ RAVI · OPEN
Seepage · L2 bath · re-testedCLOSED ✓
Every snag tied to the element it lives on
AS-BUILT MODEL · CURRENT
Duct MEP-D-0412 · shifted 4 inupdated ✓
Wall W-2041 · as drawn
The model matches the building you built
PAPERS · ON THEIR ELEMENTS
LIFT-T2-01 · load test cert
DG set · commissioning report
Fire pumps · warranty 24 mo
HANDOVER DAY · ALREADY MADE
Live model
Snag register — 0 open
Compliance stack · every document
Handed to facilities — day one ready

Hand over the building, not a box of files.

Every snag carries a photo, a voice note, an assignee and a status, tied to the element it lives on. The as-built model stays current as the real building diverges from the drawn one. Test certificates, commissioning reports and warranties attach to the elements they certify, so the paper and the thing it proves can never lose each other.

On the day, the handover package is already made: the live model, every document in its place, the snag register, the compliance stack. The facilities team receives a building they can question from day one.

06
Maintain
WHATSAPP · RESIDENT · 2:04 AM
The lift in Tower 2 is stuck between floors.
Found it — LIFT-T2-01. Pulling its file.
The asset behind the complaint, found by the system
LIFT-T2-01 · THE FILE
Warranty — active, 14 mo left
Installer · service history × 6ATTACHED
Vendor dispatched — knows it all
WARRANTIES & AMCS · ON TIMERS
Chiller AMC — lapses in 21 days
Fire pump warranty — renewed
Claim documents — one question away
THE TWIN GROWS
BMS integrated
Lift telemetryLIVE
Society inherits a continuous record

The building keeps its memory.

A resident reports a fault on WhatsApp. Korbel finds the asset behind the complaint, pulls its warranty, its installer, its service history, and dispatches the vendor with all of it. Every fault, service and part replacement logs against the asset, so the record only gets richer.

Warranties and AMCs run on timers, with alerts before they lapse, and the documents an association needs for a claim are one question away. When your maintenance window closes, the society inherits a clean, continuous record, not a mystery. And where an asset justifies it, the twin upgrades: BMS integration, then live sensor telemetry.

07
Sell
WALK IT · BEFORE IT EXISTS
FLAT 9B EXACTLY AS SOLD
YOUR HOME · MILESTONE BY MILESTONE
L9 slab poured · photo attached✓ 14 SEP
Your windows in✓ 02 OCT
Drawn live from the same site records
A SMART BUILDING · NOT JUST KEYS
Living model — systems visible
Every fitting · warranty attached
Faults report themselvesLIVE
THE RECORD · SELLS IT
What's behind this wall, exactly?
Answered from the build record — spec, installer, certificate. Booked ✓

The flat sells with its story attached.

A prospective buyer walks a flat that is not built yet, or one that is, and sees exactly what they are buying. A pre-booked customer watches their home go up milestone by milestone, drawn live from the same site records your engineers file, so the question "what is happening with my flat" answers itself. And the building you hand them is a smart one, its faults and its systems visible on a living model.

The same rigour that ran the build becomes the thing that sells it.

The subcontract module
Runs through Plan, Procure, Build and Handover.

The bill says 60 percent. The site says 45.

Somewhere between the two numbers is a fight, and it happens every month, on every package, from a standing start. Nobody measured together. Nobody wrote it down against the thing itself.

On Korbel, a subcontract package is not a paragraph of scope. It is a set of named elements, carved from the model, issued with the current drawing attached. The crew's supervisor musters labour on WhatsApp. Progress claims arrive with the photo attached, against the element it belongs to. Measurement is joint, the RA bill drafts itself, and retention, advances and debit notes run on one account both sides can see. When a back-charge comes, it comes with evidence, not a negotiation.

And the one question every subcontractor asks, when will I be paid, answers itself, straight from your accounting system to their WhatsApp.

The layer underneath

One name, carried the length of the job.

Every feature above pulls on the same record. An element is named once, in design, and everything that ever happens to it, the price, the order, the delivery, the install, the sign-off, the warranty, the 2am fault, resolves to that name. That is what makes eight tools behave like one building.

Three things make the record work in the real world:

It lives where your people live.
Site engineers, vendors, client reps and facilities teams work on WhatsApp, because that is where they already are. The model is for the people who need the model.
It checks itself continuously.
Every change to the model triggers clash, cost, schedule and quality checks the moment it lands. Problems surface in hours, not at the next coordination meeting.
People decide.
Every judgement call routes to the right role with the right context. The system compounds. The humans stay in charge.

Build it with us.

We are taking on a handful of builders as early partners, not customers.

Talk to us
{{ emailError }}
{{ doneMsg }}
×

We are excited to talk to you.

Just a couple more details.

Call me
{{ modalError }}

Privacy: your name, email and phone number are used once, to arrange this call. Korbel does not share them with anyone and deletes them on request. See our privacy policy, or write to hello@korbel.ai.

Thank you.

{{ calledMsg }}

Close
Let's carry the load.
hello@korbel.ai
Privacy · © 2026 Korbel